Tuesday, 13 December 2011

2012 Cavanacaw Goldmine Ombudsmans Report

Cavanacaw Goldmine Blog








THE OMBUDSMAN (NI) ORDER 1996

Reference: 201000847,
201000848 & 201000849

INVESTIGATION REPORT
UNDER ARTICLE 16 (1) (A)




GUIDANCE NOTE ON CONFIDENTIALITY AND PRIVLEGE





Confidentiality

As Ombudsman, I am mindful of the requirement of Article 13(3) of the Ombudsman (NI) Order 1996 to the effect that every investigation is conducted in private.  Under this legislation, I have no general power to share information with the public and I am in fact barred from disclosing any information obtained for the purposes of an investigation except in very limited circumstances.


Consequently, it is my view that the information in this Report is confidential until such times as it is published by me in accordance with the provision of the above Order.  Although ultimately a matter for the Court to decide in any case, I consider that any unauthorised publication of this report, or its contents, may breach confidentiality. 

Privilege for Certain Publications

While I enjoy absolute privilege for the purposes of the law of defamation when I publish my Report to the Northern Ireland Assembly, please note that this privilege does not extend to the publication by any person of this Report.



Report Summary

This complaint relates to an opencast gold and silver mining facility on land at Cavanacaw Upper, Botera Upper and Tattykeel Omagh and, what the complainants believe to be, the lack of appropriate enforcement action taken by PS in response to breaches of planning permission. Following an extensive public enquiry, approval for the mine was given by PS in May 1995. Preparation work for the facility commenced in May 2000 and ore processing began in January 2007. In May 2008 trucks began removing considerable volumes of rock from the mine which, the complainants believe, were to be used in local roadworks at Ballygawley. Residents complained to PS at this time. The complainants believe that PS failed to take enforcement action commensurate with the breach which had a considerable impact on their amenity. The complainants indicated to me that, at its peak, up to 145 trucks per day were leaving the site. They also complained that PS failed to effectively monitor the site and allowed the operator to alter the site without the required planning approval. The complainants also raised concerns about the handling by PS of current applications to rectify the breaches of planning control/ conditions at the mine.

Findings

My investigation indentified, what I consider to be, a major system failure by PS in its response to complaints from residents about the removal of rock from the mine. Indeed, it took PS in excess of one year to issue an enforcement notice requiring the company to cease removal of the rock. PS permitted the company to remove in excess of 8000 truck loads of rock, by the operator's own admission, without any assurance that there remained sufficient rock to restore the site to its original condition. I also found that PS failed to monitor whether the company operating the site was complying with planning conditions, a failure I consider represented maladministration.


Given the considerable loss of amenity, inconvenience and severe distress to the complainants during the removal of rock, I recommended that the Chief Executive personally issues a letter of apology, along with a consolatory payment of £10,000 to each of the three complainants.


I also recommended that a reassessment of the present position of the mine be carried out within six months of the date of my report and that PS should report its findings both to me and to the complainants.


I am aware that planning applications are currently being considered by PS to regularise a number of the breaches of planning condition/ control. Whilst it is not my role to interfere in the planning process, I can fully understand the complainant's concern given the significant failure of PS to meet its statutory responsibilities up to this point. The complete absence of effective intervention has resulted in a complete lack of confidence by the complainants in the planning process and a resultant scepticism on their part that their current concerns will be meaningfully considered by PS.


Introduction

1.  I received a complaint from xxxxxxxxxxxxxxxxxxxxxxx (the complainants) regarding the actions of the Planning Service (PS). Their complaint relates to an opencast pit for precious metal mineral extraction
operated by Omagh Minerals Ltd (OML) at Cavanacaw, Omagh and the failure of PS, in their view, to ensure compliance with the original planning approval (K/1992/0713) for the mine.


2.  In particular, the complainants believe PS failed to adequately monitor the site and when OML began removing large volumes of rock from the mine, PS
failed to take appropriate enforcement action.



3.  I am aware that on 1 April 2011, due to an organisational restructuring, the Planning Service (an Executive Agency of the Department of the Environment) ceased to exist and its function transferred to the newly created Planning & Local Government Group within the Department of the Environment.  In view
of the fact that the matters about which this complaint relates, occurred prior to

1 April 2011, I shall use the designation 'Planning Service' in this report.



Role of the Ombudsman

4.  The Ombudsman (NI) Order 1996 gives me the authority to investigate complaints from people who claim to have sustained injustice through maladministration by government departments and their agencies such asPS. It is important that members of the public who bring a complaint to me fully understand the limitations of my role in planning matters.  It is not my role to question the merits of professional or technical decisions such as those made by planning officers in the exercise of their discretion, unless there is evidence of maladministration in the reaching of such decisions or the decisions made were perverse.  I therefore look to see if there is any evidence of negligence, improper consideration or improper use of powers.  Generally I would only question a discretionary decision if it was clearly at variance with that which could be expected in the light of all the facts.  In other words it must be so unreasonable that no reasonable person would take it.


5.  My authority extends to the investigation of the administrative actions of PS.
Furthermore, disagreement  with a professional or technical decision does not in itself constitute evidence of maladministration, however unpopular or at variance that decision may be with what some interested party, or indeed I, might consider appropriate.  Unless I find evidence of maladministration which I consider has caused injustice to a complainant I cannot uphold a complaint.


Legal and administrative background

6.  The Department of the Environment is responsible for planning and managing development in Northern Ireland. The Department's statutory planning functions are primarily provided for by the Planning (Northern Ireland) Order
1991.



Planning Policy Statement (PPS) 9 -The Enforcement of Planning

Control

7.  PPS 9 sets out the general policy approach that the Department follows in taking enforcement action against unauthorised development in Northern Ireland.
8.  Paragraph 3.2 of PPS 9 advises how the Department will be guided in

considering whether formal enforcement action is an expedient remedy for unauthorised development by the following:
•   Whether the breach of control would:

(a) be clearly contrary to planning policy; or

(b) unacceptably affect public amenity (including road safety) or the existing use of land and buildings meriting protection in the public interest.
•    The extent of the breach. The Department will only pursue enforcement action commensurate with the breach of planning control to which it relates. For example, it will usually be inappropriate to issue an enforcement notice for an insignificant or technical breach of planning


control which has no material, adverse planning implications. However, in those cases where harm to public amenity has occurred, or is likely to occur, then formal enforcement action will normally be promptly initiated.
•    The willingness of the offender(s) to remedy the breach of control voluntarily. Where initial attempts by the Department fail to persuade the offender(s) to remedy the harmful effects of unauthorised development voluntarily, protracted negotiations will not be allowed to hamper or delay whatever formal enforcement action may be required
to make the development acceptable on planning grounds, or to compel it to stop.
•   The statutory time limits for taking enforcement action.

•   The integrity of the development control process depends upon the readiness of the Department to take effective enforcement action when it is appropriate. Public respect for the development control system is quickly undermined if unauthorised development, which is unacceptable on planning grounds, is allowed to proceed without any apparent attempt to intervene before serious harm to public amenity results. The Department will therefore assess in each case which
power (or mix of powers) is best suited to dealing with any particular apparent or actual breach of control to achieve a satisfactory and lasting remedy. Prompt initiation of enforcement action will normally be necessary to prevent an unacceptable breach of control becoming well established and more difficult to remedy.
•   The Government remains committed to fostering business enterprise and the Department will bear this in mind when considering how best to deal with unauthorised development by small businesses. However, in order to maintain a fair and safe trading environment, business activity must take place within the context of current planning policies and without unacceptable harm to public amenity. Accordingly in certain cases effective enforcement action may be the only appropriate remedy for unauthorised business where there is no willingness on the behalf of operators to negotiate a satisfactory solution.




9.  Paragraph 7.1 also advises: "Where, in the view of the Department, unauthorised development is causing serious harm to public amenity and there is little likelihood of the matter being resolved voluntarily or through negotiations, the Department will normally take vigorous enforcement action. This may include the service of a stop notice with, or on the foot of, an enforcement notice, or, where circumstances permit, an injunction to remedy
the breach urgently in order to prevent further serious harm to public amenity".



10. Most importantly, paragraph 9.1 of PPS9 sets out the Departments role in the enforcement of planning control over mineral working. It states: "Unauthorised mineral workings can pose particular enforcement problems in terms of the occasionally irremediable nature of the working, the speed at which significant damage to the environment can be caused, as well as the fact that there will be no agreed arrangements for the restoration or after-use of the land. Consequently in cases where formal enforcement proceedings are necessary
the Department will take prompt action and will be guided by the advice set out in section 7.0 of this Statement to ensure that the possibility of irreparable environmental damage is minimised".


Investigation

11.    have reviewed all relevant correspondence from the complainants and PS.

Additionally, I arranged for my Director of Investigation and my Investigating Officer to meet with the complainants. I also arranged for my Investigating Officer to meet with staff from PS Minerals Unit, Strategic Projects Division and also to inspect the enforcement files that relate to this complaint. I also obtained extensive documentation from PS including the papers from the public enquiry held to consider the original application (K/1992/0713) and the
Environmental Statement which accompanied the application. I also examined the relevant legislative framework. The responses from the PS Chief
Executive (CE) to my enquiries are included at Appendices 2, 4 and 6. For reference, I have included the questions posed to the CE by this office at Appendices 1, 3, and 5. The complainants raised a number of issues in their complaint which, for the purposes of this report, I have set out under the headings below (in bold), my findings of fact and conclusions.



12.    have not included in this report every detail investigated, but I am satisfied that no matter of significance has been overlooked.


(a) PS failed to issue a stop order when the company comprehensively redesigned the entire site layout without planning permission and failed to require the company to submit retrospective planning applications to rectify the breaches;
13. The complainants told me that OML completely redesigned the entire site layout and that no planning application was made despite complaints from residents in the area. They also believe that PS took little or no action against the company for these breaches of planning permission. The complainants told me that the changes at the site included changes to the site access, tailings pond, internal roads, Kerr vein and stockpiles.


14. By way of background, I noted that the original planning application (K1992/0713) was approved on 23 May 1995 following an extensive public enquiry. Condition 1 of the approval required the development to commence "not later than the expiration of five years". OML advised PS, in a letter dated the 19 May 2000, that "work commenced on site development earlier today". I also noted that ore processing commenced in January 2007.


15. One of the issues raised by the complainants related to the site access. I noted approved drawing number K/1992/0713/02 from the original approval which detailed the site plan and indicated the stage of works at the end of year two. Among other things the drawing sets out the entrance to the site during phase one. Drawing K/1992/0713/03 details the entrance to the site during phase two.


16. The CE told me in his response that the site access was included and illustrated on the approved drawings. He also explained that the operators wrote to PS on 8 May 2000 requesting an amendment to the phasing of the access. The operator requested that the phase two access be immediately available for use rather than having to implement the Phase 1 access and subsequently the Phase 2 access

17. On receipt of this request PS consulted Roads Service who informed PS that it had no objections to the amendment. PS wrote to OML on 19 May 2000 advising that the amended access was approved

18. Another issue raised by the complainants related to the tailings pond at the mine. I noted condition 10 of the original approval which stated: "The tailings dam shall be constructed generally in accordance with details shown in cross­ sections depicted in Figure 88 of the Environmental Statement." Condition 10 further advised that "the completed design for the dam structure and impoundment area shall be submitted to the Department for approval prior to construction". The CE advised that the operators submitted a conceptual design for the tailings cells system to PS on 4 March 2005 including conceptual drawings. The CE also advised that PS approved the scheme on 9 May 2005 subject to detailed drawings being submitted to PS prior to construction.


19.In his response the CE also advised that the tailings pond was included in the original planning approval and was illustrated on the approved drawings. He also advised that "the operators were keen to pursue new environmentally sensitive techniques and they commissioned some research into the benefits of Tailings Cells instead". The CE further advised that the operator submitted detailed drawings on 5 October 2005 and that "the current scheme that can be observed on site is being carried out in accordance with these drawings". He also advised that PS is awaiting information to verify that the Tailings Cells are constructed in accordance with these drawings

20. In relation to the internal roads the CE advised that the operator chose to relocate this road for operational reasons and submitted a retrospective application (K/2010/0098/F) to regularise the change

21. The CE acknowledged that the current location and shape of the stockpile storage differ from that shown in the approved drawings, however, he advised that a Breach of Condition Notice (EN/2009/0655) has been issued by PS. I noted the Breach of Condition Notice was issued on 30 November 2009 and advised that Conditions 2, 7, 17,and 39 of the original approval had not been complied with. The Notice also explained that the OML should "demonstrate by way of appropriate survey that the development is being carried out in accordance with the drawings and details bearing the Department's Drawing Number stamp with the reference K/92/0713 01-09".

22. In relation to the Kerr vein the CE advised that concerns were raised that this vein did not benefit from planning permission for extraction of ore. He advised that, having reviewed the files, it was clear that the planning permission allowed for this extraction. The CE also advised that, in response to concerns from residents about the limited detail of plans relating to this pit, PS engaged with the operators and requested detailed construction plans for the extraction of ore from the Kerr vein. Detailed drawings were submitted on 18 August 2009. The CE provided a copy of the request and response for my information. 

23. In relation to the stockpiles, the CE agreed that the current location and shape of the actual stockpile storage differed from that shown on the approved drawings. He explained that "breach of Condition Notice (EN/2009/0655) lists Condition 02 as one of the conditions considered to have been breached". He advised that Condition 02 relates to the development as having to be carried out in accordance with the approved drawings. The CE also explained that the rate of lowering and removal of stockpiles will be affected by the option of removing surplus rock, off site. He advised that enforcement action in relation to the height of the stockpiles was being "held in abeyance while the current application for the removal of surplus rock is determined".


24. In conclusion, the CE advised that "the redesign of the site in its individual elements has been a progressive issue. Each element of the redesign has been addressed by the means considered most appropriate and expedient, with reference to the terms of the original planning approval and the requirement of PPS 9. To date the service of a Stop Notice has not been considered necessary given the willingness of the operator to co-operate and where necessary submit retrospective applications to regularise breaches."


(a) Conclusions

25. It is clear from the evidence in this case, and the detail given in the CE's response, that the layout of the site differs considerably from that of the approved drawings. The operator of the mine changed the layout of the site without the prior approval of PS, although I am aware that the company has submitted retrospective planning applications to rectify these breaches. I consider PS has an important responsibility to ensure facilities, such as the mine at Cavanacaw, are properly monitored to enforce planning laws, especially in relation to applications which are attended by considerable public attention and objections. I have expanded on my view on this matter later in my report. The enforcement action taken by PS only commenced following receipt of complaints from local residents in June 2008 regarding breaches at the site. Given the site development commenced in May 2000 and ore processing from January 2007, I find it wholly unacceptable that PS failed to observe that the layout of the site had changed considerably from that of approved plans and associated drawings and failed to take appropriate action.


26.  I consider the failure of PS to proactively monitor this site to represent maladministration. In cases where I identify maladministration, I must consider the injustice caused to the complainant(s). In reaching my opinion of this aspect of this complaint, I do not, however, consider that the complainants suffered a personal injustice as a result of the failure by PS to monitor the site in respect of changes to the layout. Whilst the layout of the site had changed without planning approval, I do not consider this impacted on the amenity enjoyed by the complainants. I therefore, am unable to uphold this aspect of their complaint.


27. Whilst I did not consider that the complainants suffered a personal injustice as a result of this failure, I do, however, believe it highlights a complete inadequate approach on the part of PS in its monitoring of the mine at Cavanacaw.

(b) PS provided misleading/incorrect advice in particular in relation to a site survey, restoration of the site and the Kerr Vein;

28.In his reply to my enquiries the CE advised that, throughout the investigation of this case, PS has maintained communications with all parties involved, including the complainants. The CE also advised that the local residents met with the Minister to discuss the issues raised by them. The CE did not agree that PS misinformed complainants with regard to the commissioning of surveys at the mine

29. The CE explained that two officers from PS visited the mine on 26 November2008 to investigate a number of alleged breaches of planning control. Whilst on site the officers attempted to take a number of readings in relation to the width, depth and length of the pit, along with the height of the stockpile but unfortunately the equipment available to the officers was not suitable, as a consequence of the scale of the site. The CE advised that Mr Shankly was notified of this in writing on 18 December 2008.


30. The CE advised that the operators of the mine submitted a Closure Plan on 20March 2009 that included data from a survey which it had carried out. The survey was forwarded to the Department of Finance and Personnel's (DFP) Central Procurement Directorate (CPO) but due to IT compatibility reasons it could not be read. The CE also advised that PS, through a procurement process, secured  the services of CPO to undertake a survey of the mine, however, "the scale and nature of the site posed operational and safety constraints that prevented CPO from obtaining the survey data that PS had requested". The CE also advised that Mr Shankly was again informed of this, in letters dated 1 and 22 July 2009.


31. The CE also advised that following further discussion, CPO agreed to explore the possibility of placing a tender request for a suitably qualified company to carry out the survey. The CE advised that CPO provided an indication of the likely costs of the survey on 31 July 2009. Given the scale of the estimate
involved, the CE advised that PS concluded that "this level of expenditure could not be justified given its budgetary constraints" and "the earlier request for CPO to explore the tender process was therefore terminated".


32. The CE explained that OML confirmed that a specialist company had been commissioned to carry out a laser survey of the site and Mr Shankly was informed on 3 September 2009 that PS would be requesting a copy of this survey. In a further letter dated 30 November 2009 Mr Shankly was informed that PS had requested this survey from the operators and that the earlier survey would not now be commissioned by PS. The CE advised that this was explained by the Divisional Planning Manager in his letter of 18 January 2010 to Mr Shankly.


(b) Conclusion

33.    I noted a letter, dated 26 February 2009, issued by email to Mr Shankly from an officer from the Minerals Unit, PS, who advised that "the Planning Service are concerned with Land Use Planning only and on occasion will employ the services of qualified professionals to undertake work that Planning Service are unable to carry out. The Department has secured the services of a qualified surveyor to carry out this work".


34.also noted a letter, dated 18 January 2010, from the Strategic Projects Manager (SPM) in response to the complaint from Mr Shankly, when he explained that two officers from the Department visited the gold mine on 26
November 2008 and attempted to take a number of readings in relation to the width, depth and length of the pit, along with the height of the stockpile. The SPM advised that the equipment available to the two officers was "unsuitable and thus incapable of taking readings on the scale required".


35. It is clear to me that the officers from PS experienced difficulties carrying out the site survey due to the unavailability of suitable equipment. PS also engaged the in-house technical services of CPO, however, due to the scale of the site, CPO was unable to carry out the survey. The possibility of employing an external surveying company to carry out the survey was considered, however, this was not pursued due to the considerable costs that would be involved. It is clear to me, however, that the letter of 26 February 2009 did lead the complainants to believe that a survey would be commissioned. I cannot, however, conclude that PS deliberately misled the complainants. It was the case that there was considerable communication between PS and a number of residents at that time regarding various breaches of planning
control. Whilst the letter issued by PS did lead the complainants to believe that a survey was to be carried out, I believe the position as it unfolded was clearly explained in subsequent letters. I am, therefore, unable to reach a definitive conclusion on this aspect of the complaint.


36. Whilst, I was unable to conclude that PS deliberately mi"sled the complainants in relation to the site survey, I feel I must comment on the lack of appropriate action taken by PS when a survey of the site, forwarded by the operator, could not be read by CPO "due to IT compatibility reasons". Given the considerable objections and complaints raised by the residents regarding the ability to restore the site following the removal of the rock, I find it inconceivable and unacceptable that PS failed to ask the operator to provide the survey in a format that could be read.  Such a basic failure yet again highlights the half­ hearted approach taken by PS in relation to its monitoring of the mining
facility.



(c) PS took 8 months  to issue a stop order with regard to the unauthorised removal of rock from the site and failed to require the company  to submit a retrospective planning  application to rectify this breach.  Also, PS took 8 months to issue a stop order with regard to up to 145 trucks per day unlawfully entering  and leaving  the site over a seven  month period to remove rock from the site and failed to require the company  to submit a retrospective planning  application to rectify this breach

37. In his response the CE advised that the initial breach in relation to the  unauthorised removal of rock was reported to PS in June 2008.  The CE advised that PS visited the site on 9 June 2008 and made contact with the operators on 16 June 2008, followed by a site meeting on 1 August 2008.


38. The CE advised that the removal of rock ceased following negotiations with
the operator which resulted in an undertaking being provided by OML. The CE
advised that the removal of rock required for restoration ceased on 6 February
2009. The CE explained that, during this period, PS engaged with DRD Roads Service, and with the operator on the interpretation of the original planning condition. He also advised that advice was sought from the Departmental Solicitor's Office.


39. A further report was received by PS on 17 June 2009 that removal of rock had recommenced. The CE advised that an Enforcement Notice (EN/2009/0270) was issued on 30 June 2009. The CE also explained that a Stop Notice was not necessary given that the initial breach was ended through negotiations and the subsequent recommencement ceased following the serving of the  Enforcement Notice.

40. The CE advised that the operators submitted a planning application (K/2008/0995/F) to vary condition 39 in an attempt to remedy this breach. However, in a subsequent reply to enquiries from this office, the Deputy Secretary (Acting) advised that this was in fact incorrect and that "in the Department's view, the unauthorised development (removal of rock) and the subsequent volume of traffic that had been entering and leaving the site on a daily basis was unacceptable and planning permission was unlikely to have been granted. In these circumstances a retrospective application would not have been appropriate".  The CE advised that OML also submitted a Closure Plan in accordance with condition 39 which would allow for the removal of surplus rock from the site at a stage earlier than previously envisaged. The application proposes an amendment to allow for the Closure Plan to be implemented at any stage (progressively) rather than within six months of the cessation of ore processing. The CE advised that this application is still under consideration. 

41. I noted that PS received a telephone call on 4 June 2008 advising that rock was being taken off-site by a contractor to roadworks at Dungannon. The caller advised that the removal of rock started on 26 May 2008 and localresidents were concerned about damage to the local roads. A further call was received on 6 June 2008 advising that the lorries were leaving the site from 6.50am and estimated 30-40 lorries on a daily basis. The caller complained that the roads were being damaged

42. On 16 June 2008 PS contacted the mine manager to advise that the 
Department had received a number of complaints in relation to material 
leaving the site. The mine manager confirmed that the material being removed was waste rock and was being used in the Ballygawley road scheme. He also explained that the anticipated rock to be removed was in the region of several million tones and would be removed over a number of years. The mine manager also questioned what condition he was breaching. 

43.   I  noted a letter from the Managing Director, OML, dated 24 June 2008 toPS explaining that "by disposing of the surplus rock on an ongoing basis, rather than waiting until the last moment permitted under the consent, we have reduced the environmental landscaping tail to the project, reduced the additional visual impact where all such material to be stored during the project, reduced the peak stress upon local roads by spreading in time the off-take of such material and enhanced the security of satisfactory project completion arrangements".


44. I noted the letter from the PS Special Studies Section to the Managing Director, OML, dated 9 July 2008, which stated "whilst it may have always been the intention of the company to integrate the surplus rock into the local aggregate environment, it is evident that this intention was insufficiently highlighted or included in the Environmental Statement, PAC Report or indeed the planning approval under K/1992/0713/F". The letter also advised that OML should "contact the Department to discuss the submission of a retrospective planning application should the company wish to regularise this breach of planning control".  I noted the application (K/2008/0995/F) was received by PS on 26 September 2008

45. On 10 October 2008 two officers from PS visited the site. In their notes of the
visit the officers recorded that "in a timeframe of 10-15 minutes" they witnessed and recorded 11 lorries. The notes also record that the officers met with the site manger and "outlined the Departments view on the breach of condition and explained the options that Planning Service had available to them under the Planning Legislation to remedy the breach, including the issuance of a Stop Notice. The operator was advised to look at possible ways to address the situation before formal legal action was required". 

46.In a letter from the Chief Executive, Omagh District Council, dated 28 
November 2008, to the Principal Planning Officer, the Chief Executive outlined concerns expressed by members of the Council, which included the removal of rock from the site. The Council's Chief Executive extended an invitation to the Principal Planning Officer to address a meeting of the Council's Planning and Public Services Liaison Committee

47. On 27 January 2009, the mine manager wrote to PS regarding the amendment to condition 39. In his letter the mine manager stated: "from 6th February PT McWilliams will cease drawing stocked rock from site. It is likely that further surplus rock will have to be removed from site; however they will not do so until the determination of the amendment has been made and traffic levels agreed with the department, provided that determination of the amendment is achieved within a reasonable time. Omagh Minerals undertake this action not because we believe we are in breach of our planning permission but we wish to demonstrate co-operation and enable the department to demonstrate improved amenity for local residents to the minister". 

48. also noted the mine manager set out the company's proposal for HGV movements. He stated: "We propose that future movements are limited to a maximum of 40 loaded lorries leaving site per day. This represents a significant decrease from the current maximum that reached 145 loads per day.

49. In a further letter from the mine manager to PS, dated 23 March 2009, he
advised that 8213 truck loads of stone had been removed  from site equating to 82,000 cubic metres (broken). 

50. On 17 June 2009, PS received  a telephone  call advising  that a tractor and trailer was removing  rock from the site to use in a laneway.  Enforcement  file K/2009/0096/CA was subsequently  opened. PS contacted  the mine manager on 21 June 2009 who advised that three loads had been removed.  PS carried out a site visit on 22 June 2009 when officers observed  rock being removed from the mine

51. On 30 June 2009 an enforcement  letter was issued to OML to "cease removal of rock within 24 hours of this notice". I noted the enforcement file is now closed, however,  the enforcement  notice remains in place. 

(c) Conclusion 

52.In reaching my conclusions on this aspect of the complaint, I have examined carefully the considerable documentation associated  with this case, including the Environmental Statement  which accompanied the original planning application  and the documentation from the public enquiry. I also arranged for my Investigating Officer to examine all the enforcement  files in relation to the mining facility at Cavanacaw

53. I noted that the use of the local road network is referenced  at Page 11, paragraph  four of the Environmental Statement  accompanying the original application,  advising that "The minor roads around the site are narrow and have limited potential for the regular movement  of heavy loads. However,  such loads will be restricted  to the supervised  transport of excavating machinery and plant components to and from the site during the preconstruction and decommissioning phases". Paragraph  six further clarifies the issue: "During operations,  traffic will be largely confined to light vehicles.  Total traffic generated  is estimated  as 60 to 75 movements  per day of light vehicles and one lorry load of fuel or other supplies per day (my emphasis).  This level of vehicle activity is low and will not affect the capacity of the local road network".

 54. Paragraph C10.3 of the Environmental Impact Assessment (EIA) included in the Environmental Statement also highlights issues surrounding the local road network: "The proposed vehicular route to the site would cross the bridge listed as number 1 on Figure C13. This is considered to be of local interest. Heavy vehicles, such as those delivering plant and equipment, will be supervised over this bridge. The vehicles which are expected to traverse other routes are not exceptionally large nor heavy, and are expected to have minimal impact on cultural heritage"

55. Paragraph C11.3 of the EIA also states: "The proposed development will generate a limited amount of heavy traffic during the construction phase, notably in connection with the movement to site of the excavators and haulage vehicles and the components of the process plant. During the operational phase requirements will largely be confined to light vehicles. Following completion of construction and commissioning, there will be no requirement for the transport of heavy materials to and from the site until the decommissioning phase (my emphasis), when plant and salvageable materials will be removed from the site... Light vehicular traffic, principally conveying site personnel and visitors, may approach the site from various directions. An estimate of the number of vehicle movements per day for normal site activities is given in Table C11. 3. The majority of car movements will occur at the beginning and end of the day shift". I have included a copy of Table C11.3 at Appendix 7.  

56. In summary, paragraph C11.5 of the EIA states "The proposed development will have very little impact on the local infrastructure, which has plenty of capacity to meet the site's requirements. The level of vehicle traffic is low and will not affect the capacity of the local road network. All deliveries and removal of heavy equipment will be via the north, and under close supervision".                                                                                                                           .
 57. 1t is clear that the mine operator had a different interpretation of the planning approval than that of PS in relation to the removal of rock. The operator believed Condition 39 allowed for the disposal of waste rock. Condition 39 (b)
of the approval states "the refilling of the trench with waste rock to the level of the surrounding land and the disposal of surplus rock." In its letter to the operator dated 9 July 2008, PS stated "whilst it may have always been the intention of the company to integrate the surplus rock into the local aggregate environment, it is evident that this intention was insufficiently highlighted or included in the Environmental Statement, PAC Report or indeed the planning approval under K/1992/0713/F". 

58. Having carefully reviewed the Environmental Statement and the Public Enquiry Documentation, I agree with the interpretation of PS in this respect. It is clear that it was never the intention, during the consideration of the initial planning application, that rock would be removed from the mine. There are also numerous references within the documentation accompanying the Public Enquiry which also reinforce this view. Of particular importance is section eight of the Public Enquiry which outlines the position of the Department, the applicant, third parties and the consideration of the Public Enquiry. For completeness, I have included this section of the Public Enquiry, in its entirety at Appendix 8.  

59. PS set out its position at a very early stage in its letter of 9 July 2008, some four weeks after the initial report of rock removal from the mine. However, the complainants are at a loss to understand why PS took in excess of one year from the date of the initial report (4 June 2008) to the issuing of an enforcement notice (30 June 2009), given the significant breach of planning approval and the potential impact on the environment and local residents. The mine manager freely admitted in his letter of 27 January 2009 that a maximum of 145 trucks per day were removing rock from the site at that time. Indeed, when PS official visited the site on 10 October 2008 they recorded 11 lorries leaving the site in a period of 10-15 minutes

60. Planning Policy Statement (PPS) 9 sets out the general policy approach the Department will follow in taking enforcement action against unauthorised development. Paragraph 3.2 states "In considering whether formal enforcement action is an expedient remedy for unauthorised development, the Department will be guided by the following: 

•   whether the breach of control would: 

 (a) be clearly contrary to planning policy; or
   (b) unacceptably affect public amenity (including road safety) or the existing use of land    and buildings meriting protection in the public interest. 

61. The CE told me that on 6 February 2009 "the alleged unauthorised traffic movements associated with the removal of rock from the site had ceased following negotiations with OML". I note paragraph 3.2 of PPS 9 further clarifies the Department's role in enforcement: "Where initial attempts by the Department fail to persuade the offender(s) to remedy the harmful effect of unauthorised development voluntarily, protracted negotiations will not be allowed to hamper or delay whatever formal enforcement action may be
required to make the development acceptable on planning grounds, or to compel it to stop. "(my emphasis) 

62. Paragraph 7.1 of PPS9 also states "where, in the view of the Department, unauthorised development is causing serious harm to public amenity and there is little likelihood of the matter being resolved voluntarily or through negotiations, the Department will normally take vigorous enforcement action. This may include the service of a stop notice with, or on the foot of, an enforcement notice, or, where circumstances permit, an injunction to remedy the breach urgently in order to prevent further serious harm to public amenity".  
  
63.    I noted with particular interest section 9.0 of PPS 9 which sets out the Departments policy in respect of enforcement of planning control over mineral working. Paragraph 9.1 states: "Unauthorised mineral workings can pose particular enforcement problems in terms of the occasionally irremediable nature of the working, the speed at which significant damage to the environment can be caused, as well as the fact that there will be no agreed arrangements for the restoration or after-use of the land. Consequently in cases where formal enforcement proceedings are necessary the Department will take prompt action and will be guided by the advice set out in section 7.0of this Statement to ensure that the possibility of irreparable environmental damage is minimised". 

64. Given the Department's policy on enforcement action which I have highlighted in the above paragraphs, I find it wholly unacceptable that PS failed to take appropriate timely enforcement action commensurate with this breach of planning control given the very significant impact this had on local residents, including the complainants. The failure of PS to take appropriate enforcement action is even more difficult to understand given that it issued an enforcement notice in June 2009 when its officers witnessed a trailer load of stones being removed from the site yet failed to do so when, by the companies own admission, up to 145 trucks per day were leaving the site and, indeed, when PS officials witnessed 11 lorries leaving the site over a short period of 10-15 minutes in October 2008. 

65. Where the exercise of discretion is involved, I carefully consider whether, in my view, this discretion has been exercised reasonably and without maladministration. I can only question a discretionary decision if I regard it as being wholly unreasonable  that no reasonable person would take it in the light of the relevant facts and circumstances. The decision on whether to take enforcement action is an example of a discretionary decision. It is clear from the Public Enquiry held to consider the initial planning application for the mine that the prospect of a mining facility attracted considerable opposition from a variety of sources in the Omagh area. Indeed, Appendix 8 demonstrates the importance given to the issue of traffic to and from the mine by the Public Enquiry

66.   I  can fully understand the frustration of the complainants and the other residents at the lack of effective enforcement action taken by PS. The Chief Executive, Omagh District Council also corresponded with PS outlining the Council's concerns at the rock being removed from te site yet no action was taken by PS to stop the removal. In response to enquiries from this office the PS CE advised that the delay was as a result of negotiations with the mine operator along with a request for legal advice. Whilst it is the case that officers did visit the site promptly after receipt of the first report of the lorries leaving the site, it is my considered opinion that the subsequent lack of timely enforcement action by PS was attended by maladministration.   Indeed, the interpretation of the planning approval by PS was clearly set out in its letter of 9 July 2008. Why PS allowed the mine operator to continue to remove up to 145 trucks of rock per day from the site, for a period of approximately eight months, given PS's clear understanding of the restrictions of the original planning approval, is quite astonishing and demonstrates a complete failure to protect the public interest.
    


67. Inaction such as this clearly undermines the public's expectation of the planning process. Indeed PPS 9 highlights this particular issue: 'The integrity of the development control process depends upon the readiness of the Department to take effective enforcement action when it is appropriate. Public respect for the development control system is quickly undermined if unauthorised development, which is unacceptable on planning grounds, is allowed to proceed without any apparent attempt to intervene before serious harm to public amenity results". 

68. Notwithstanding the issue of traffic to and from the mine, the complainants also raised concerns about the restoration of the site. I can fully understand their concern given the large volume of rock removed from the site given that, by its own admission, the operator removed some 8213 truck loads of stone equating to 82, 000 cubic metres from the site. It is inconceivable that PS continued to allow the operator to remove huge volumes of rock from the site without any assurance that there remained sufficient rock to backfill the trench, a failure which, in my view, also represents maladministration. Indeed, PS has confirmed that officers were unable to measure the size of the trench and rock pile on the site. As such, it had no confirmation that there remained on site enough rock to fully restore the mine to its former condition as outlined in the original Public Enquiry

69. In its consideration of the original planning approval considerable importance was given by the Public Enquiry to the restoration of the site and how the land would be restored to its original condition. The CE confirmed that PS was not treating application K/2008/0995/F as a retrospective application as the volume of traffic would not have been acceptable. In effect, other than the Enforcement Notice issued in June 2009, the removal of the rock over the period June 2008 to February 2009 has been allowed without planning approval. Whilst planning application (K/2008/0995/F) submitted by the mine operator on 26 September 2008 was to vary condition 39 of the original approval, to allow progressive restoration, I believe PS clearly should have taken more effective, robust and timely enforcement action following the initial complaints from residents in June 2008. I, therefore, uphold this aspect of their complaint. 

(d) there has been delay in or a general lack of enforcement by PS 

70. 1n his response to my enquiries the CE provided a chronology of the enforcement action taken by PS in this case. I have provided a copy of this at Appendix 9

71. noted the original approval (K/1992/0713), issued on 23 May 1995, included 
40 conditions. The CE advised that PS received confirmation on 24 May 2000 that the company had commenced operations on site on 19 May 2000. The CE also advised that the plant at the site became operational on 22 January 2007 when the company commenced the processing of ore

72. Whilst an enforcement case (K/2006/0139CA) had been opened in
December2006 to investigate alleged breaches with regard to conditions relating to noise monitoring, the first enforcement action taken by PS following the commencement of ore processing was as a result of the report of rock removal received on 4 June 2008. Subsequent to this PS took enforcement action in relation to additional breaches such as unauthorised screening and crushing plant; hard surfacing of internal roads; internal road not located in accordance with the approved drawings. In addition to the Enforcement Notice issued on 30 June 2009 in relation to the removal of rock from the mine, the CE advised that PS issued a Breach of Condition Notice (EN/2009/0655) in respect of conditions 02, 07, 17, and 39.



 (d) Conclusion

73. I noted condition 39 of the original approval stated: "within 5 years of the date of commencement of this development, or within 3 months of a written request from the Department, the operator shall provide for the agreement of the Department, a Closure Plan for the development; such a plan to be implemented within 6 months of cessation of ore processing.


74. Condition 1 also states that "the development must be begun not later than the expiration of five years beginning with the date of this permission as required by Article 34 of the Planning (Northern Ireland) Order 1991". The CE advised that the company  notified PS in a letter dated 19 May 2000 that site development  had commenced.  Given this start date it follows that the Closure Plan should have been submitted to PS no later than May 2005.


75.  noted paragraph  19.43 of the Public Enquiry where the Commissioner  stated "As Dr Johnson  has persuaded  me that it is physically  possible to successfully restore the site at Cavanacaw  I have only one remaining  concern. That concern, and I am aware that it is a concern raised by many of the objectors,
is that OML will be able to fully implement the restoration  scheme. Should planning permission be granted for this proposal I consider it to be essential (my emphasis)  that any consent makes provision to ensure that OML, or any consent makes provision  to ensure that OML, or any successor  company, can be made to fully implement  any Restoration (or Closure) Plan".


76. As highlighted in PPS 9 the key objectives for planning enforcement must be secured "otherwise the credibility and integrity of the planning system will be undermined".  This view was reinforced by the Criminal Justice Inspection (CJI) Northern Ireland, in its report of October 2007, in relation to enforcement in the Department of the Environment  (DOE) and its Executive  Agencies, including PS. In relation to PS, the report concluded that "PS needs to be seen as committed to tackling breaches  of the regulations. That commitment needs to be sharpened  to ensure that there is a systematic means of progressing all relevant cases through to the right outcome. There should be little room for a soft option' of restoration  only, no offender should be able to negotiate their way out". The report also stated that there was "a lack of clarity on work priorities and a lack of focus on enforcement.  These pressures are de­ motivating staff and causing inequality and inconsistency  of approach as staff look for 'quick wins' to close cases. Additionally, the CJI report stated "there is some ambiguity around what is meant by 'commensurate' or 'expedient' which often leads to staff taking the 'soft' option. There is a need for more clarity around these elements to improve the efficacy of enforcement actions and show greater determination to enforce planning laws, to their full extent".


77.I note that an initial closure plan was submitted on 20 March 2009 with a final version of the closure plan submitted in February 2011. Given that the Closure Plan should have been submitted to PS no later than May 2005 (paragraph 74 refers), I consider the failure of PS to ensure the closure plan was submitted within the timescales permitted in the original approval to constitute maladministration. Indeed, the sole purpose of condition 39 was to ensure a closure plan would be submitted which set out the mine operator's proposals for restoration of the site. It was only following local residents raising their concerns regarding the removal of rock that any action was taken by PS, albeit over a year after the initial approach from residents.


78. As part of my investigation, I also examined the documentation relating to Enforcement Notice EN/2009/0270 which was issued on 30 June 2009. The Enforcement Notice highlighted the breach of planning control, in particular, the "unauthorised removal of rock required under K/1992/0713 for restoration of the site, from lands at Cavanacaw, Omagh. " I asked the Deputy Secretary (Acting) if an Environment Impact Assessment (EIA) had been carried out by PS in accordance with paragraph 23.1 of Development Control Advice Note (DCAN) 10 which states that "the Department is required to make an EIA determination accordingly and issue it with the enforcement notice". In her reply the Deputy Secretary (Acting) advised that the Department did make an EIA determination but did not issue it with the enforcement notice. The Deputy Secretary (Acting) also advised that the Department concluded that the removal of rock did not constitute EIA development and that the determination was not issued with the Enforcement Notice. The Deputy Secretary (Acting) explained that the wording in paragraph 23.1 of DCAN 10 is "a little unclear in terms of the circumstances in which an EIA determination is to be issued with an enforcement notice." She further advised that, under Regulation 22 of The Planning (Environmental Impact Assessment) Regulations (NI) 1999, PS was not required to issue a negative determination with the enforcement notice.


79.   I noted that PS determined that the breach of planning control did not fall within the scope of Schedule 1 of The Planning (Environmental Impact Assessment) Regulations (NI) 1999. I asked the Deputy Secretary (Acting) for an explanation as to how this determination was reached given that the Regulations classify a Schedule 1 development as "Quarries and open-cast mining where the surface of the site exceeds 25 hectares, or peat extraction where the surface exceeds 150 hectares". I noted the P1 form accompanying the original application for the mine gives the area of the site to be 60 hectares

80. 1n her response, the Deputy Secretary (Acting) advised that "the determination was reached by consideration of the development associated with the breach i.e. the removal of the rock". She also advised that the size of the site for the original application (K/1992/0713) was not a factor for consideration in this determination

81.    am confused with this determination given the Enforcement Notice (EN/2009/0270) issued on 30 June 2009 related to "land at Cavanacaw Gold Mine, Botera Upper Road, Cavanacaw, Omagh shown edged in red on the attached plan". The attached plan (Appendix 10) outlines the mine in its entirety. 

82. PS records show that an Environmental Statement was not required for the following reason(s): "The breach involves the removal of this rock from the site to other locations in haulage vehicles travelling along the public road network. The proposal does not fall within Schedule 1 but does fall within Schedule 2 of The Planning (Environmental Impact Assessment) Regulations (Northern Ireland) 1999. It is considered that the removal of rock from the site would not have significant environmental impacts and that indeed the problems and concerns associated with this type of development could be dealt with and taken into consideration in the normal planning process and through the submission of additional information if required." I find this statement confusing given that the determination also states that "the rock is to be used to restore the site after the operations are completed. The rock is to be used to backfill the pit and create landfilling features". 

83. The complainants have asked how the rock can be used to restore the site
when it has been removed and used in road building. I can fully understand this concern. I am also concerned with the determination that the proposal does not fall within Schedule 1, given the size of the site (60 hectares) and the area outlined in the map accompanying the Enforcement Notice. The EIA determination also states that an environmental statement was not required as "this type of development could be dealt with and taken into consideration in the normal planning process and through submission of additional information if required". I find this statement conflicts with the Deputy Secretary's (Acting) confirmation that the "volume of traffic that had been entering and leaving the site on a daily basis was unacceptable and planning permission was unlikely to have been granted".  

84. Given the lack of supporting explanation, I consider the decision to classify the proposal as a Schedule 2 development during the EIA determination inspect of enforcement notice EN/2009/0270 to be attended by maladministration


Overall conclusions

85. Having considered the large volume of documents from both the complainants and PS, I have identified a number of instances of maladministration in the enforcement action taken by PS. In particular PS
    failed to stop the operator removing up to 145 truck loads of rock per day from the site for a period of approximately eight months without any assurance that sufficient rock remained on the site to backfill the trench already excavated;
   failed to ensure the closure plan was submitted within the timescales permitted in the original approval;
   failed to adequately document the decision to classify the proposal as a Schedule 2 development in the EIA determination carried out as part of enforcement notice EN/2009/0270

86. I   did consider the letter issued by PS in respect of the commissioning of a survey of the site by PS to be misleading, however, I was unable to reach a definitive decision on whether PS deliberately misled the complainants. I also identified maladministration in the failure of PS to proactively monitor the site following a redesign by the operators, however: I did not consider the complainants suffered any injustice as a result of this failure

87. Whilst I am aware that the majority of enforcement action taken by PS is by its nature reactive, in cases such as this, which have both the potential to and the actual effect of impacting on the environment and the amenity of local residents, I consider it essential that PS take proactive enforcement action to ensure full compliance with planning approvals. Members of the public need to be assured that public bodies such as PS are taking appropriate and timely action to ensure activity of this nature complies with the conditions set out in the planning approval. This is essential if public confidence and trust in the role of PS is to be secured and maintained

88. Notwithstanding the failure of PS to proactively monitor the mine, PS also failed to take timely enforcement action following complaints from local residents. I have no doubt the failure by PS to take appropriate robust enforcement action has caused the complainants considerable anxiety, inconvenience, distress, frustration and loss of amenity. Despite repeated complaints from local residents regarding the movement of up to 145 trucks per day from the mine, PS allowed this breach to continue for a period of eight months. In every respect, the action taken by PS fell significantly short of what I consider to be appropriate in this case. I have not been presented with any
evidence to demonstrate that PS took appropriate action to ensure planning conditions were adhered to in order to ensure the public confidence in the planning system. The failures identified in my report highlight what I consider to be a major system failure in the monitoring and effective, prompt enforcement action taken by PS in relation to the mining facility at Cavanacaw.  

89. Given what I consider to be the considerable injustice caused to the complainants in this case, I recommend that the CE personally issues a letter of apology along with a consolatory payment of £10,000 to each of the three complainants. I also recommend that PS carries out, or commissions external consultants to carry out, and complete a reassessment  of the present position of the mine within six months of the date of this report. In particular, the report should detail the level of rock remaining on the site and whether this is sufficient to restore the site to its previous condition. PS should report its findings both to me and to the complainants, and should then consider any recommendations to protect the amenity of the area and the site that may be judged necessary in light of its conclusions

90. 1n conclusion, my investigation has highlighted the failures of PS to effectively monitor and enforce planning control/ conditions at the precious metal mine, I also believe it is important to comment on, what I consider to be, my very serious concerns regarding road safety for residents, pedestrians and other users of the road network around the mine at Cavanacaw. When rural roads, such as those leading to the mine at Cavanacaw, are used so intensively by large vehicles to transport heavy loads, road safety must be the primary consideration not only for PS, but for other authorities such as Roads Service and the PSNI, who also should be proactive in monitoring risk. I would expect, therefore, that PS in future engage with other authorities when difficulties such as these are identified to ensure a more integrated approach is taken to address the concerns and potential risks to road users and residents. I also will have an expectation that the Roads Service, in cases such as this, proactively pursue a more robust approach in order to achieve its key objective in promoting road safety and importantly protect road infrastructure from damage due to unplanned use.

  Assembly Ombudsman


 Cavanacaw Goldmine Blog